Lister Building Demolition Works

Please note there are some demolition works being carried out around the Lister Building, from 13th Nov to 31st March 2018.  The schedule of works is listed below.

Please note there will be closure of Warnock St. and re-routed “assisted” access to buildings so please make alternative arrangements where necessary.

  • Fri 3rd, Sat 4th and Sun 5th November - Burns Unit Diversion Ramp Installed.
  • Mon 6th Nov - “Road closed on 13th Nov” signs being erected to inform road users of Warnock St. closure.
  • Saturday 11th Nov – Burns unit Ambulance bay being hatched and “Ambulance/Drop off only” sign being erected.
  • Saturday 11th Nov and Sunday 12th Nov - 1 metre extension to existing footpath turning point to be installed.
  • Monday 13th November – Warnock St. closed , Compound Fencing erected, Grahams Cabins/welfare arriving.
  • Contract completion date is 31st March 2018.

Further signage will be in place on Wishart St. and Queen Elizabeth Building to direct pedestrian “assisted” traffic to access “link corridor” to Walton Building.

We apologise for any inconvenience this may cause, and thank you for your co-operation during this period.